FUNDING PROGRESS (as of January 14, 2014)
Keep updated on the funding progress by checking back to this tracker. Help us reveal the whole picture of the school design! (Click image to see it enlarged.) Current Progress, as of 1/14/2014: $130,000 of $220,000–59% funded–$90,000 left to go
BUILDING PROGRESS (as of January 14, 2014)
Walls going up on the first three classrooms. Three classrooms funded; three to go.
Day we broke ground-October 15, 2013